SMC Development
Horizon production transfer → Sintercom, India
EVR half-ring
185 Half-Ring

Horizon currently manufactures the part, holds quality approvals, and ships to the customer. This plan tracks the India localization work.
Launch scenarios
Planning assumptions & unresolved gates
First incomplete activity in the plan
Customer readiness targets shown below
Activities & proposed dates
Release gates
Customer schedules
Original inputs retain the supplier plan and Napino Control Systems’ 4 Nov update. Edit whole component parts below. Demand and opening inventory are shared across both configurations; US/India arrival assumptions are separate.
Each month: prior net balance + usable arrivals − demand = new net balance. A positive balance is on-hand stock; a negative balance is backorder. Backorders are already included in net balance and are not subtracted twice. Each source arrival is counted once, in its arrival month. Do not enter production, dispatches, in-transit quantities, or an internal transfer twice. Blank means unknown; enter 0 only to model none. Unknowns carry forward until the missing input is supplied.
Calculated balances cannot be overwritten. Change opening stock, demand or arrivals to update them consistently. No safety-stock target, lead-time order sizing, or intra-month availability guarantee is assumed. Products are separate and cannot be added together as complete motors.
Restore all original inputs? This resets shared demand/opening stock and both configurations’ arrivals, and removes your saved browser copy. The shared HubSpot page and CRM records are unchanged.
Configuration comparison
Same demand and opening stock, separate arrival plans. First shortfall is the first known month-end backorder; any missing earlier month can make that timing uncertain.
Opening inventory and arrivals are entered in whole parts. Component-set equivalents use 4 half rings or 6 central forks and are rounded only for display. Opening backorders are assumed zero; enter only usable opening stock. No shipment or purchase order is created by editing.
Launch Gantt chart
Activities and sourcing gates from the selected scenario, through April 2027.
Bars show planning windows, not commitments. Dashed outlines identify conditional downstream work. Undated cure acceptance stays visible; it can push every later milestone. Weekends and supplier calendars are not validated.
Process & packaging concepts
Proposed concepts for review. Equipment specifications and packaging selections remain subject to confirmation.
Machine & disc brush concept
Continuous brush rotation with a part fixture, reversing part motion, pneumatic slide, and dust collection.
- Filament
- Silicon carbide
- Brush type
- Disc
- Size
- 260 × 35 mm
- “Grit size” in PDF
- 0.75 mm — specification to confirm
- Quoted cost
- Approx. 30K; currency not specified

Grid & separator packaging
PP grid, PP separator, PP sleeve, cap, pallet, and lashing.

Box ID 1140 × 740 × 615 mm · OD 1200 × 800 × 780 mm
Pocket 159.5 × 79 × 25 mm
Formed pocket packaging
PP pocket trays, PP sleeve, cap, pallet, and lashing.

Box ID 1140 × 740 × 615 mm · OD 1200 × 800 × 780 mm
Items to align with Sintercom
- Localisation PO is reported as not received as of 3 November 2026.
- Confirm furnace calibration and first cure test dates; neither is separately scheduled on page 4.
- Confirm customer approval and procurement release gates: the proposal ends L&T sample submission on 24 January, with readiness requested by end-January. No separate Napino Control Systems sample submission date is supplied. Contingency dates are scenario assumptions derived from the current approved plan, not revised supplier commitments.
- Confirm OD 155 versus OD 185, the brush “grit size” specification, and the cost currency before finalizing the plan.