▥ Gantt chart
Sintercom / HORIZON / INDIA LOCALIZATION
ESTABLISHED PRODUCTION
HALF-RING
LOCALIZATION
INDIA LOCALIZATION
HALF-RING LOCALIZATION • SUPPLIER PROPOSAL · 03 NOV 2026

SMC Development

Horizon production transfer → Sintercom, India

Confidential Technology TRANSFER

EVR half-ring

185 Half-Ring
Half-ring component with radial inner teeth, front view
Front view
Half-ring component showing the reverse face
Reverse view
✓
Established at Horizon. Preparing for Sintercom.

Horizon currently manufactures the part, holds quality approvals, and ships to the customer. This plan tracks the India localization work.

CURRENT PRODUCTION ACTIVE
TWO TIMELINES · ONE DEMAND MODEL

Launch scenarios

Shared demand & opening stock

Planning assumptions & unresolved gates
    ACTIVITIES COMPLETE
    1 / 147%
    NEXT OPEN ACTIVITYLocalisation PO

    First incomplete activity in the plan

    LAUNCH TARGETCustomer specific ◇

    Customer readiness targets shown below

    THE LOCALIZATION PLAN ·

    Activities & proposed dates

    Complete Planned
    ACTIVITY / PROCESSSTART / ENDSTATUSREMARKS
    DECISION POINTS

    Release gates

    EDITABLE DEMAND & INVENTORY

    Customer schedules

    View original demand source ↗

    Original inputs retain the supplier plan and Napino Control Systems’ 4 Nov update. Edit whole component parts below. Demand and opening inventory are shared across both configurations; US/India arrival assumptions are separate.

    Editable planning inputs · automatic month-end calculations

    Each month: prior net balance + usable arrivals − demand = new net balance. A positive balance is on-hand stock; a negative balance is backorder. Backorders are already included in net balance and are not subtracted twice. Each source arrival is counted once, in its arrival month. Do not enter production, dispatches, in-transit quantities, or an internal transfer twice. Blank means unknown; enter 0 only to model none. Unknowns carry forward until the missing input is supplied.

    Calculated balances cannot be overwritten. Change opening stock, demand or arrivals to update them consistently. No safety-stock target, lead-time order sizing, or intra-month availability guarantee is assumed. Products are separate and cannot be added together as complete motors.

    Configuration comparison

    Same demand and opening stock, separate arrival plans. First shortfall is the first known month-end backorder; any missing earlier month can make that timing uncertain.

    Opening inventory and arrivals are entered in whole parts. Component-set equivalents use 4 half rings or 6 central forks and are rounded only for display. Opening backorders are assumed zero; enter only usable opening stock. No shipment or purchase order is created by editing.

    THE PLAN AT A GLANCE

    Launch Gantt chart

    Activities and sourcing gates from the selected scenario, through April 2027.

    Aug 31, 2026 – Feb 7, 202714 activities · 13 with dates · 1 complete
    CompleteIn progressNot startedBlocked

    Bars show planning windows, not commitments. Dashed outlines identify conditional downstream work. Undated cure acceptance stays visible; it can push every later milestone. Weekends and supplier calendars are not validated.

    SUPPORTING DETAIL · PDF PAGES 5–7

    Process & packaging concepts

    Proposed concepts for review. Equipment specifications and packaging selections remain subject to confirmation.

    01 / DEBURRING

    Machine & disc brush concept

    Continuous brush rotation with a part fixture, reversing part motion, pneumatic slide, and dust collection.

    Filament
    Silicon carbide
    Brush type
    Disc
    Size
    260 × 35 mm
    “Grit size” in PDF
    0.75 mm — specification to confirm
    Quoted cost
    Approx. 30K; currency not specified
    Sintercom’s deburring machine schematic and silicon carbide disc brush photograph
    02 / PACKAGING CONCEPT 01

    Grid & separator packaging

    PP grid, PP separator, PP sleeve, cap, pallet, and lashing.

    1,260 parts / box 63 parts × 20 layers
    Packaging concept 1 with grid separator, exploded box view, and part arrangement

    Box ID 1140 × 740 × 615 mm · OD 1200 × 800 × 780 mm
    Pocket 159.5 × 79 × 25 mm

    03 / PACKAGING CONCEPT 02

    Formed pocket packaging

    PP pocket trays, PP sleeve, cap, pallet, and lashing.

    880 parts / box 44 parts × 20 layers
    Packaging concept 2 showing formed half-ring pockets and exploded packaging view

    Box ID 1140 × 740 × 615 mm · OD 1200 × 800 × 780 mm

    Items to align with Sintercom
    • Localisation PO is reported as not received as of 3 November 2026.
    • Confirm furnace calibration and first cure test dates; neither is separately scheduled on page 4.
    • Confirm customer approval and procurement release gates: the proposal ends L&T sample submission on 24 January, with readiness requested by end-January. No separate Napino Control Systems sample submission date is supplied. Contingency dates are scenario assumptions derived from the current approved plan, not revised supplier commitments.
    • Confirm OD 155 versus OD 185, the brush “grit size” specification, and the cost currency before finalizing the plan.